Roofs make of metal tiles are prevalent among consumers. If you are a filmmaker’s type of roof, you should know that its installation must be ok strictly according to all the standards and instructions. Otherwise errors and violations. Will appear after a long time. And this kind of roofing will have to be ready again. To prevent this, clearly follow all the steps describe below
We will make a plan to track the progress of the work.:
- Calculate the number of metal tiles.
- Rafter system.
- Cornice board installation.
- Install the front board and file the overhang.
- Sewer hook installation.
- Installing waterproofing and installing counter mesh.
- Placing planks around chimneys, ridges, and skylights.
- Eaves mount.
- Lower valley installation.
- Place an apron around the chimney pipe.
- Laying metal sheets.
- End Plate Installation.
- High valley installation.
- Ridge battens and exterior corner installation.
- Sewer installation.
- Roof grounding.
- Post-assembly work (cleaning, repainting)
Let’s consider each item in detail.
- Calculate the number of metal tiles
Metal tile sheets are sold. Each such sheet has a complete and usable width. Usable width is always 8-12 cm smaller than the full width. For this reason, only the usable width of the sheet is considered. Metal roofing San Antonio to get better services in your home. To calculate the required number of sheets, the maximum length of the horizontal slope is divided by the proper width of the sheet. The results are round.
The length of the sheet is calculated as follows:
- Measure the length of the slope from Eve to the ridge;
- Take into account the overhang from the cornice, which is 5 cm;
- Consider the total overlap of all the sheets, which is 15 cm for each row;
- Add all previous points.
- Rafter system
The rafter can be use in two sections: 15×5 and 10×5 cm. However the distance between them has been select from 60 to 90 cm. If you want to use long distances, you need to use a crate (extra transverse board). The humidity of the wood should not exceed 22%. Be sure to treat the plant with a fire extinguisher and antiseptic agent. To make the roof rectangular, again, measure the length of all the slopes diagonally. Note that the minimum roof slope should not exceed 14 degrees.
- Installation of the cornice board
The cornice board is design to give the whole structure the necessary rigidity. It is mount under the sewer hook in the grooves make in the rafter.
- Sewer hook installation
All sewers are plant on long hooks. These are attach either to the rafters. Or to the cornice board. This must be ready before laying the metal tiles. The pitch of the hook must match the pitch of the rafter. Previously, hooks were groove in the rafters for the legs.
So many roof installations in San Antonio companies. Are available near you. They are then bent into the grooves make. And screw with screws from the end. or top of the rafter. In cases when metal tiles are already lay they do this. They are not long but use short. Hooks install on the front board.
That is, we divide the area of each slope in half. And get the area of the ventilation slot.
Airflow will be provided: ventilation gap between filing eaves; Gaps between waterproofing and roofing, thermal insulation and waterproofing; The gap around the ridge.